We are currently on track for our December launch – below is a summary of progress:
BT circuits are in to the majority of service provider sites with work progressing to plan at others; we still read delivery dates a little cautiously given the delays experienced in other areas of the UK although Surrey has fared better in general. Interface equipment for studios is being built ready for delivery and installation. We are tentatively looking at installing the multiplex rack and having some live data running through the systems in mid-November.
On the transmitter side there is lots underway:
Guildford –
- Telemetry circuit delivery planned 25/10/13
- Build to commence first week of November
- Commissioning requested w/c 18th November
Reigate –
- Telemetry Circuit complete
- Decommissioning of existing racks completed this week
- Build to commence w/c 27th October
- Commissioning requested w/c 18th November
Crystal Palace –
- Build completion due early next week.
- Commissioning requested w/c 11th November